Traffic Management in The Grove

Screen-Shot-2017-12-26-at-4.33.31-PM.png

Work on the Timbergrove/Seamist Proposed Traffic Management plan continues following public meetings earlier in 2017. According to Khang M. Nguyen, Assistant Director, Traffic Management Branch, City of Houston, more than 190 comments were received on the plan, with more than 60 percent supporting speed cushion installation.

The original plan has been modified to reduce the number of cushions on east-west streets. Nguyen estimates construction will start in February. “After the cushions are in place for at least 90 days, we’ll conduct an ‘after’ traffic study and then hold the third public meeting to present the study results and solicit further input from the residents.”